Hockey

Northeastern’s New Arena Delayed Until 2029 After Asbestos Discovery

Construction setbacks push back the multimillion‑dollar project, leaving the hockey team without a permanent home for an extra season.

Northeastern University announced this week that the construction of its much‑anticipated multi‑purpose arena will not be finished until spring or summer 2029, pushing the opening back by nearly a year.

Why the delay matters for the hockey program

The delay means the men’s and women’s hockey teams will continue to play their home games at a patchwork of nearby facilities for the next three seasons, extending a period without a dedicated venue that was already slated to last two years.

University officials said the setback stems from a combination of structural complications and the discovery of asbestos‑containing materials during early site preparation, forcing a pause in work and a costly remediation process.

A historic venue bites the dust

The new arena is meant to replace Matthews Arena, a landmark that has served the campus since 1910, first as Boston Arena, then as a multi‑sport facility that hosted countless games and community events.

Demolition crews completed the removal of the aging structure in March after engineers determined that the building suffered from severe structural decay and that the surrounding soil was contaminated with asbestos and other hazardous substances.

The $350 million project, approved by the board of trustees in 2022, was billed as a state‑of‑the‑art facility designed to anchor the university’s athletic ambitions and to provide a modern recruiting tool for the hockey program.

University President Renu Khator said the administration remains committed to the vision of a dedicated arena, but the timeline will be reassessed as the remediation work progresses and as the institution evaluates financing options.

In the meantime, the athletic department has secured temporary agreements with several local venues, including the nearby TD Garden and the Boston Common rink, to host home games while the new site prepares for construction.